Constructing Capacity (Southern Region), MW
Q3, 2020
Wind Turbines Sold (3S), MW
Q1, 2020
Wind Turbines Sold, MW
Q3, 2020
| Metrics | FY, 2017 | FY, 2018 | FY, 2019 |
|---|---|---|---|
| Constructing Capacity (Southern Region), MW | 50 | 200 | 122 |
| Wind Turbines Sold (3S), MW | 45 | 342 | 701 |
| Wind Turbines Sold, MW | 5.1K | 5.9K | 8.2K |
| Order Backlog (Signed Contract), MW | 9.4K | 12.9K | 14.4K |
| Order Backlog (Successful Bid), MW | 6.5K | 5.7K | 5.8K |
| Order Backlog (Internal Order), MW | 602 | 1.5K | 671 |
| Order Backlog, MW | 16.5K | 20K | 21K |
| Connected and Installed Capacity, MW | 3.9K | 4.7K | 4.7K |
| Constructing Capacity, MW | 1.5K | 2.8K | 2.9K |
| Constructing Capacity (Overseas), MW | 690 | 1.2K | 966 |
| Constructing Capacity (East China), MW | 565 | 718 | 650 |
| Constructing Capacity (North China), MW | 150 | 275 | 785 |
| Order Backlog (Overseas), MW | 704.5 | 656.6 | 1.5K |
| Utilization, hours | 2K | 2.2K | 2.2K |
| Constructing Capacity (Northeastern), MW | 42 | 98 | 200 |
| Wind Turbines Sold (1.5 MW), MW | 627 | 360 | 131 |
| Wind Turbines Sold (2S), MW | 3K | 4.4K | 4.7K |
| Wind Turbines Sold (2.5S), MW | 1.4K | 745 | 2.4K |
| Under-construction and Signed Contract Capacity, MW | 1.5K | 1.3K | |
| Wind Turbines Sold (6S), MW | 54 | 253 | |
| Constructing Capacity (Northwestern), MW | 250 | 200 | |
| Power Production, MWh | 7.6M | 7.8M | |
| Backlog (Domestic) | ¥488.5M | ¥817.6M | |
| Under-operation Fleet, MW | 7K | 11K |
Community
Employees
Environment
Governance
Source:CSRHub